Sokhna 500 \220 KV GIS

A fresh achievement for Arcon Group !!!

In Sokhna station with L&T...

We constructed the building under the High Voltage lines of 500kV within the Range of impact of their electromagnetic fields, As the high voltage lines were shouted-off for only 5 hours to allow us to finish and Pure the roof of 220kV building. and the whole shutting offs schedule was veary tight and challenging that gave use a very narrow periods to finish all of our constructions that required a very complected technique and implementation methods. .

The excavation of the project began for the first building on th December 2018 and all the constructions for the entire project buildings were completed on 11th of March 2019,  Despite all tough conditions and challenges, the entire concrete constructions were accomplished within 92 days...