A Fresh Achievement for Arcon Group...

A Fresh Achievement for Arcon Group...

In Sokhna Station with L&T...

The construction of the buildings under the high-Voltage lines of 500 KV and within the range of impact of their electromagnetic fields within the schedule of switching off the electrical current during the casting only for very short periods through a complicated work techniques and methods of implementation and insulation difficulties. Today, the 500kV lines are switched off for only five hours, to finish and pour the roof of the 220 KV building the last roof of the project and we built an hour before operating an hour for metal roof at a height of 15 meters. Thus, the Arcon heroes completed all concrete structures for all buildings under these tough conditions. The excavation of the project began for the first building on 9 December 2018. All structures for all the project buildings were completed on 11 March 2019. Despite these conditions, all the concrete structures of the project buildings were completed within 92 days…